1. BenCo makes and sells pots. the manufacturing process has twostage : Fabrication and Painting. The pots are fabricated in onebuilding and then transferred to painting shed to the finished.When the paint has cured, the pots are transferred to the finishedpot showroom.
manufacturing overhead is applied to the Fabrication area basedon DL Hours incurred in the paint area.
expected paint DL Hours for January 2016-220 DL hours.
Expected paint overhead- $4620
Beginning and ending inventory balance for January
materials inventory fabrication WIP Painting WIP Finished potsinventory
1/1/16 $5000 $1000 $2000 $3000
1/31/16 $4000 $2000 $1000 $5000
During January of 2016:
BenCo purchased $30,000 of materials
Incurred $11,000 of direct labor( 550 DL Hours@ $20 per DLHours) in the fabrication area
Incurred $5000 ( 200 DL Hours @ $25 per DL Hours) in the paintarea
incurred manufacturing overhead in the fabrication area totaling$24,000
incurred manufacturing overhead in the paint areatotaling $4000
Required
a. what is cost of goods manufactured for January 2016?
b. what is cost of goods sold for January 2016 before closingany over/under applied overhead to COGS?
c. what is COGS if any over/under applied overhead is closed toCOGS?
1. BenCo makes and sells pots. the manufacturing process has twostage : Fabrication and Painting. The pots are fabricated in onebuilding and then transferred to painting shed to the finished.When the paint has cured, the pots are transferred to the finishedpot showroom.
manufacturing overhead is applied to the Fabrication area basedon DL Hours incurred in the paint area.
expected paint DL Hours for January 2016-220 DL hours.
Expected paint overhead- $4620
Beginning and ending inventory balance for January
materials inventory fabrication WIP Painting WIP Finished potsinventory
1/1/16 $5000 $1000 $2000 $3000
1/31/16 $4000 $2000 $1000 $5000
During January of 2016:
BenCo purchased $30,000 of materials
Incurred $11,000 of direct labor( 550 DL Hours@ $20 per DLHours) in the fabrication area
Incurred $5000 ( 200 DL Hours @ $25 per DL Hours) in the paintarea
incurred manufacturing overhead in the fabrication area totaling$24,000
incurred manufacturing overhead in the paint areatotaling $4000
Required
a. what is cost of goods manufactured for January 2016?
b. what is cost of goods sold for January 2016 before closingany over/under applied overhead to COGS?
c. what is COGS if any over/under applied overhead is closed toCOGS?