Hickory Company manufactures two products—14,000 units ofProduct Y and 6,000 units of Product Z. The company uses aplantwide overhead rate based on direct labor-hours. It isconsidering implementing an activity-based costing (ABC) systemthat allocates all of its manufacturing overhead to four costpools. The following additional information is available for thecompany as a whole and for Products Y and Z:

Activity CostPool ActivityMeasure Estimated Overhead Cost Expected Activity
Machining Machine-hours $ 203,000 10,000 MHs
Machine setups Number of setups $ 121,900 230 setups
Productiondesign Number of products $ 87,000 2 products
General factory Direct labor-hours $ 379,500 12,000 DLHs

ActivityMeasure Product Y Product Z
Machine-hours 7,300 2,700
Number ofsetups 50 180
Number ofproducts 1 1
Directlabor-hours 9,500 2,500


1. What is the company’s plantwide overhead rate? (Roundyour answer to 2 decimal places.)

2. Using the plantwide overhead rate, how much manufacturingoverhead cost is allocated to Product Y and Product Z?(Round your intermediate calculations to 2 decimal placesand final answers to the nearest dollar amount.)

3. What is the activity rate for the Machining activity costpool? (Round your answer to 2 decimal places.

4. What is the activity rate for the Machine Setups activitycost pool?

5. What is the activity rate forthe Product Design activity cost pool?

For unlimited access to Homework Help, a Homework+ subscription is required.

Jamar Ferry
Jamar FerryLv2
28 Sep 2019

Unlock all answers

Get 1 free homework help answer.
Already have an account? Log in

Related questions

Weekly leaderboard

Start filling in the gaps now
Log in