Can you help me confirm the calculations on this assignmentproject has the following estimates for net cash flow.
Year Pessimistic Cash Flow Estimate Most Likely Cash Flow Estimate Optimistic Cash Flow Estimate 1 $14,000 $20,000 $22,000 2 $19,000 $25,000 $30,000 3 $27,000 $30,000 $36,000 4 $32,000 $35,000 $39,000
At the beginning of this four-year project, the project costs are expected to be $65,000 and no expenses will be incurred thereafter. (a) Compute the cash flow for each year using the three-point estimation technique. (b) Assuming an inflation rate of 3% and the required rate of return of 8%, compute the net present value of the project.
Can you help me confirm the calculations on this assignmentproject has the following estimates for net cash flow.
Year | Pessimistic Cash Flow Estimate | Most Likely Cash Flow Estimate | Optimistic Cash Flow Estimate |
1 | $14,000 | $20,000 | $22,000 |
2 | $19,000 | $25,000 | $30,000 |
3 | $27,000 | $30,000 | $36,000 |
4 | $32,000 | $35,000 | $39,000 |
At the beginning of this four-year project, the project costs are expected to be $65,000 and no expenses will be incurred thereafter. (a) Compute the cash flow for each year using the three-point estimation technique. (b) Assuming an inflation rate of 3% and the required rate of return of 8%, compute the net present value of the project.