Consider the following activity-on-node (aon) project (activity completion times are in days): refer to the figure. What is the critical path: abdf, abef, acdf, acef, none of the above. How long will take to complete the project: 15 days, 14 days, 13 days, 12 days, 11 days. What is the slack time, in days, associated with activity e: 1, 2, 0, 3, 4. What is the slack time, in days, associated with activity d: 0, 1, 2, 3, 4. Suppose that additional resources are provided to crash the project completion time below its expected normal completion time. Which activities would be potential candidates for crashing: b, d, a and b, a and d, f. What are the immediate successor(s) of activity c: d, e, d and e, a, b and d. What are the immediate predecessor(s) of activity d: b and c, b, c, c and e, b and e.