International Business Administration PMP201 Lecture 7: Ex.7_SAP_PS
Document Summary
The first activities of the project are executed. Confirmations are posted for some of the activities. Deviations from planned dates (e. g. delays) result in a shift of subsequent activities. For the exercises of this part you need a windows client with sapgui (for windows), since the project planning board graphic does not support the javagui. If you work with javagui, neglect this part and continue with exercises from 1. 8. 2. Post activity confirmations for your project p/ 20## . For this purpose open your project p/ 20## using the project planning board. Project project planning board change project (cj2b) In the selection screen please use the following data: In thedetail screen of the confirmation, please use the following data: Value as earliest scheduled start as earliest scheduled start plus 3 weeks. Return to the overview of the project planning board. Notice the date shift not only for activity 0010, but for all of its successors.