A total of 1,000 parts needs to be produced in a week. Each part is identical and requires a milling machine, and each part requires 12.5 minutes to be produced. It takes 2.5 hours to set up each machine (0.5 per day, 5 days per week), with a total of 40 hours available in a week.  How many milling machines are needed?