BTM 480 Study Guide - Final Guide: Design Structure Matrix, Mind Map, Risk Management

126 views2 pages

Document Summary

Various functional mangers understand their responsibilities and have committed to develop an initial task and resource plan. Any potential bene ts to the org outside the scope of the project are notes: how to build a wbs for the project in a straightforward and conceptually simple way. Start with objectives and divide into more precise task till it can"t be decomposed: 1 - project objectives. 2 - list of major activities to accomplish objectives (2 to 20) level 1. 3 - each level 1 activity is delegated to individual or functional group. 4 - list of level 2 task that helps completed level 1 tasks. (5 to 15) 5 - continue decomposing until lowest level are understood and no reason to continue. ** lowest level tasks will have a duration of a few hours to a few days: visual approach that mirrors the brain.