A manufacturing company that has only one product has established the following standards for its variable manufacturing overhead. Variable manufacturing overhead standards are based on machine-hours.


Standard hours per unit of output 2.90 machine-hours
Standard variable overhead rate $10.65 per machine-hour


The following data pertain to operations for the last month:


Actual hours 9,700 machine-hours
Actual total variable manufacturing overhead cost $95,750
Actual output 2,400 units


What is the variable overhead rate variance for the month?

$7,555 F

$7,836 F

$7,555 U

$7,836 U