Lipex, Ltd., of Birmingham, England, is interested in cuttingthe amount of time between when a customer places an order and whenthe order is completed. For the first quarter of the year, thefollowing data were reported:
Inspection time 0.2 days Process time 2.9 days Wait time 16.8 days Queue time 4.2 days Move time 1.1 days
Required: 1. Compute the throughput time. (Round your answer to 1decimal place.)
Throughput time days
2. Compute the manufacturing cycle efficiency (MCE) for thequarter. (Round your intermediate calculations to 1 decimalplace and final answer to 2 decimal places.)
Manufacturing cycleefficiency
3. What percentage of the throughput time was spent innonâvalue-added activities? (Round your answer to nearestwhole percent. Omit the "%" sign in your response.)
Nonâvalue-addedthroughput time %
4. Compute the delivery cycle time. (Round yourintermediate calculations and final answer to 1 decimalplace.)
Delivery cycletime days
5. If by using Lean Production all queue time can be eliminated inproduction, what will be the new MCE? (Do not roundintermediate calculations. Round your answer to2 decimal places.)
New manufacturingcycle efficiency
Lipex, Ltd., of Birmingham, England, is interested in cuttingthe amount of time between when a customer places an order and whenthe order is completed. For the first quarter of the year, thefollowing data were reported: |
Inspection time | 0.2 | days |
Process time | 2.9 | days |
Wait time | 16.8 | days |
Queue time | 4.2 | days |
Move time | 1.1 | days |
Required: | |
1. | Compute the throughput time. (Round your answer to 1decimal place.) |
Throughput time | days |
2. | Compute the manufacturing cycle efficiency (MCE) for thequarter. (Round your intermediate calculations to 1 decimalplace and final answer to 2 decimal places.) |
Manufacturing cycleefficiency |
3. | What percentage of the throughput time was spent innonâvalue-added activities? (Round your answer to nearestwhole percent. Omit the "%" sign in your response.) |
Nonâvalue-addedthroughput time | % |
4. | Compute the delivery cycle time. (Round yourintermediate calculations and final answer to 1 decimalplace.) |
Delivery cycletime | days |
5. | If by using Lean Production all queue time can be eliminated inproduction, what will be the new MCE? (Do not roundintermediate calculations. Round your answer to2 decimal places.) |
New manufacturingcycle efficiency | |