Lipex, Ltd., of Birmingham, England, is interested in cuttingthe amount of time between when a customer places an order and whenthe order is completed. For the first quarter of the year, thefollowing data were reported:

Inspection time 0.2 days
Process time 2.9 days
Wait time 16.8 days
Queue time 4.2 days
Move time 1.1 days
Required:
1.

Compute the throughput time. (Round your answer to 1decimal place.)

Throughput time days
2.

Compute the manufacturing cycle efficiency (MCE) for thequarter. (Round your intermediate calculations to 1 decimalplace and final answer to 2 decimal places.)

Manufacturing cycleefficiency
3.

What percentage of the throughput time was spent innon–value-added activities? (Round your answer to nearestwhole percent. Omit the "%" sign in your response.)

Non–value-addedthroughput time %
4.

Compute the delivery cycle time. (Round yourintermediate calculations and final answer to 1 decimalplace.)

Delivery cycletime days
5.

If by using Lean Production all queue time can be eliminated inproduction, what will be the new MCE? (Do not roundintermediate calculations. Round your answer to2 decimal places.)

New manufacturingcycle efficiency

For unlimited access to Homework Help, a Homework+ subscription is required.

Nestor Rutherford
Nestor RutherfordLv2
28 Sep 2019

Unlock all answers

Get 1 free homework help answer.
Already have an account? Log in

Related questions

Weekly leaderboard

Start filling in the gaps now
Log in