Orange County Chrome Company manufactures three chrome-platedproducts—automobile bumpers, valve covers, and wheels. Theseproducts are manufactured in two production departments (Stampingand Plating). The factory overhead for Orange County Chrome is$224,698.

The three products consume both machine hours and direct laborhours in the two production departments as follows:

Direct LaborHours MachineHours
Stamping Department
Automobile bumpers 556 795
Valve covers 297 557
Wheels 342 602
1,195 1,954
Plating Department
Automobile bumpers 165 1,169
Valve covers 179 713
Wheels 180 759
524 2,641
Total 1,719 4,595

The management of Orange County Chrome Company now plans to usethe multiple production department factory overhead rate method.The total factory overhead associated with each department is asfollows:

1

Stamping Department

$111,135.00

2

Plating Department

113,563.00

3

Total

$224,698.00

Required:
1. Determine the multipleproduction department factory overhead rates, using direct laborhours for the Stamping Department and machine hours for the PlatingDepartment.
2.

Determine the product factory overhead costs, using themultiple production department rates in (1).

1. Determine the multiple production department factory overheadrates, using direct labor hours for the Stamping Department andmachine hours for the Plating Department.

Stamping Department: per direct laborhour
Plating Department:

per machine hour

2. Determine the product factory overhead costs, using themultiple production department rates in (1).

1

Automobile Bumpers

Valve Covers

Wheels

2

3

4

Total

For unlimited access to Homework Help, a Homework+ subscription is required.

Keith Leannon
Keith LeannonLv2
28 Sep 2019

Unlock all answers

Get 1 free homework help answer.
Already have an account? Log in
Start filling in the gaps now
Log in