E-7-4 - Please explain how you arrived at your answers.Thank you!

Exercise 7-4 Second-Stage Allocation [LO4]

Larner Corporation is a diversified manufacturer of industrialgoods. The company’s activity-based costing system contains thefollowing six activity cost pools and activity rates:

Activity CostPool ActivityRates
Supporting directlabor $9 per direct labor-hour
Machineprocessing $3 per machine-hour
Machine setups $40 per setup
Productionorders $150 per order
Shipments $120 per shipment
Productsustaining $775 per product
Activity data have been supplied forthe following two products:

Total Expected Activity

J78 W52
Directlabor-hours 1,125 40
Machine-hours 2,600 30
Machine setups 11 1
Productionorders 11 1
Shipments 22 1
Productsustaining 1 1
Required:

Determine the total overhead cost that would be assigned to eachof the products. (Omit the "$" sign in yourresponse.)

Activity CostPool J78 W52
Supporting directlabor $ $
Machineprocessing
Machine setups
Productionorders
Shipments
Productsustaining
Total overheadcost $ $

For unlimited access to Homework Help, a Homework+ subscription is required.

Hubert Koch
Hubert KochLv2
28 Sep 2019

Unlock all answers

Get 1 free homework help answer.
Already have an account? Log in

Related questions

Weekly leaderboard

Start filling in the gaps now
Log in