Pryad Corporation makes ultra-lightweight backpacking tents.Data concerning the company's two product lines appear below:

Deluxe Standard
Direct materials perunit $ 73 $ 46
Direct labor perunit $ 13.00 $ 9.00
Direct labor-hoursper unit .50 DLHs 0.50 DLHs
Estimated annualproduction 22,000 units 76,000 units

The company has atraditional costing system in which manufacturing overhead isapplied to units based on direct labor-hours. Data concerningmanufacturing overhead and direct labor-hours for the upcoming yearappear below:

Estimated totalmanufacturing overhead $303,800
Estimated totaldirect labor-hours 49,000 DLHs

Required:
1.

Determine the unit product costs of the Deluxe and Standardproducts under the company's traditional costing system.(Round your intermediate and final answers to 2 decimalplaces. Omit the "$" sign in your response.)

Deluxe Standard
Unit productcost $ $
2.

The company is considering replacing its traditional costingsystem for determining unit product costs for external reports withan activity-based costing system. The activity-based costing systemwould have the following three activity cost pools:

Expected Activity

Activities andActivity Measures Estimated
Overhead Cost
Deluxe Standard Total
Supporting directlabor (direct labor-hours) $ 171,500 11,000 38,000 49,000
Batch setups(setups) 61,600 180 100 280
Safety testing(tests) 70,700 24 76 100
Total manufacturingoverhead cost $ 303,800

Determine the unit productcosts of the Deluxe and Standard products under the activity-basedcosting system. (Round your intermediate and final answersto 2 decimal places. Omit the "$" sign in yourresponse.)

Deluxe Standard
Unit productcost $ $

For unlimited access to Homework Help, a Homework+ subscription is required.

Jean Keeling
Jean KeelingLv2
28 Sep 2019

Unlock all answers

Get 1 free homework help answer.
Already have an account? Log in

Related questions

Weekly leaderboard

Start filling in the gaps now
Log in