Consider two mutually exclusive projects. The crossover rate for the two projects is 12%, at which point both have an NPV of $5,000. At a discount rate of 10%, Project 1 has a higher NPV than Project 2.
a. If the appropriate discount rate is actually 15% (not 10%), which project is better? Explain your answer.
b. Draw a rough sketch of NPVs and the crossover point to illustrate your answer. Use the following additional information as needed: Project 1âs IRR is 15%. Project 2âs IRR is 22%. Label the information provided on your graph.
Consider two mutually exclusive projects. The crossover rate for the two projects is 12%, at which point both have an NPV of $5,000. At a discount rate of 10%, Project 1 has a higher NPV than Project 2.
a. If the appropriate discount rate is actually 15% (not 10%), which project is better? Explain your answer.
b. Draw a rough sketch of NPVs and the crossover point to illustrate your answer. Use the following additional information as needed: Project 1âs IRR is 15%. Project 2âs IRR is 22%. Label the information provided on your graph.