Process Analytics Final Study Guide
• Developing the Schedule:
o Earliest Start Time (ES):
▪ the earliest start time of the immediately preceding activity
o Earliest Finish Time (EF):
▪ a activity’s earliest start tie ES) plus its estimated during (t)
• EF = ES + t
o Latest Start Time (LS):
▪ the latest finish time of the immediately preceding activity
o Latest Finish Time (LF):
▪ a activity’s attest start tie LS plus its estiated duratio t
• LF = LS + t
o Activity Slack:
▪ the maximum length of time that an activity can be delayed without
delaying the entire project
• S = LS – ES or S = LF – EF
▪ If slack = 0, then LS and ES are equal or LF and EF are equal
• indicates that on critical path
▪ Why is it important to have an estimate of slack?
• In case something goes wrong, need contingency
• May want to use contractors in this area