BUSFIN 4220 Study Guide - Final Guide: Net Present Value
Document Summary
Get access
Related Questions
Your company Portfolio Manager is convening a review board in the first calendar quarter to consider three projects. You have been asked to provide recommendations with respect to the capital budgeting aspects of these projects. Your recommendations will be considered by the review board along with other non-financial aspects of the projects. Initial (year 0) funding will be provided in the current year for the single project selected.
Project sponsors have provided the following estimated cash flow projections:
Project A | Project B | Project C | |||||||
Year | Outflow | Inflow | Netflow | Outflow | Inflow | Netflow | Outflow | Inflow | Netflow |
0 | 15000 | -150000 | 15000 | -150000 | 20000 | -200000 | |||
1 | 20000 | 20000 | 130000 | 40000 | -9000 | 150000 | -150000 | ||
2 | 30000 | 30000 | 50000 | 50000 | 90000 | 90000 | |||
3 | 40000 | 40000 | 60000 | 60000 | 100000 | 100000 | |||
4 | 40000 | 40000 | 90000 | 90000 | 110000 | 110000 | |||
5 | 50000 | 50000 | 90000 | 90000 | 120000 | 120000 |
The company has not yet decided how the selected project will be financed. The cost of capital or hurdle rate will vary depending upon how the company decides to finance the project. You decide to compare projects in three areas: (1) payback period (not considering the cost of capital); NPV sensitivity (see note 1 below); and (3) Internal Rate of Return (IRR). Conduct each analysis and interpret the results.
Based on your analysis, which project would you recommend and why? Your recommendation must be based on the combination of all three factors.
Show all calculations supporting your recommendation. Calculate NPV to the nearest dollar, IRR to three decimal places, and payback period to one decimal place.
Note 1: Project NPV varies inversely with the cost of funds to perform the project (expressed as the hurdle rate or k in the NPV discount factor formula). Some project NPVs are more sensitive to changes in k than others. See the NPV Profile discussion in Gallagher, Chapter 10, pages 278-279 for information on determining NPV sensitivity.
Question 13 Your firm has bonds outstanding with 18 years remaining until maturity. The bonds are trading for $1127 and pay a 8.5% coupon rate. Your firm faces a 32% tax rate. Based on this, the after-tax cost of debt financing is
None of the other answers are correct |
7.23% |
8.50% |
4.92% |
5.78% |
Question 14 You have estimated the following values for dividends over the next four years.
D1 = $1.50
D2 = $2.50
D3 = $3.50
D4 = $4.50
In addition, you anticipate that you can sell the stock four years from today (immediately after you receive the year four dividend) for $50. Assuming a 9% required return, the value of the stock today is
$44.79 |
$45.64 |
$41.87 |
$49.49 |
Question 15 Developed equity markets have seen higher returns than emerging equity markets over the the Nov. 2004 to June 2012 time frame.
True |
False |
Question 16 You are evaluating a capital budgeting project that will cost $25,000
Year 1 ==> $12,000
Year 2 ==> $20,000
Year 3 ==> $9,000
The required return is 13% and the critical acceptance level is 1.9 years. Calculate the Internal Rate of Return and determine whether or not the project should be accepted based solely on the Internal Rate of Return.
The IRR is 21.33% and we should reject the project |
The IRR is 17.27% and we should accept the project |
The IRR is 17.27% and we should reject the project |
The IRR is 21.33% and we should accept the project |
None of the other answers is correct |
Question 17 Linda is saving for retirement and would like to accumulate $800,000 at her retirement. She currently has $30,000 saved and would like to work for another 25 years. She plans to save $3500 at the end of each year over the next 25 years. What rate of return must she earn on her investments over the next 25 years?
10.95% |
12.45% |
8.76% |
7.23% |
9.42% |
Question 18 Consider two projects:
Project A Project B
PP 2.8 years 3.0 years
IRR 12.5% 13.3%
NPV -$15,500 -$16,900
Assume that the projects both have a required return of 15% and a critical acceptance level (T) of 3.25 years. If these are independent projects we should
Take both projects A and B |
Take project B and reject project A |
Take neither project |
Take project A and reject project B |
Question 20 Your firm wants to raise $4924796 by issuing preferred stock. The stock has a par value of $50 and pays a 6% dividend, how many shares must be issued if the required return is 10% (ignore costs associated with issuing the shares known as floatation costs -- round to the nearest share)?