Chapter#08 1. Discuss each of the following objectives listed and the relationship each has with job shop performance a. Reduce WIP inventory b. Provide a high level of customer service c. Reduce worker idle time d. Improve factory efficiency a) WIP inventory is Work-In-Progress inventory. This refers to inventory waiting to be processed and inventory currently being processed. Since there are opportunity costs associated with holding inventory (discussed in detail in Chapter 4), the firm would like to reduce the WIP inventory as much as possible. However, too low levels of WIP inventory could make coordination of separate processes difficult. b) Customer service can be measured by fill rate, namely the proportion of demands satisfied (discussed in detail in Chapter 5). The likelihood of meeting scheduled deliveries increases if jobs can flow quickly and smoothly through the system. This measure of performance could suffer if WIP inventories are reduced too severely. c) Idle time results when the smooth flow of goods is interrupted and workers must wait. Obviously, idle time is undesirable and can be very costly to the firm. d) One measure of factory efficiency is the relationship between the cost of running the factory and the revenue generated by the goods it produces. Factory efficiency can be improved by increasing the plant’s throughput rate. 5. Five jobs must be scheduled for batch processing on a mainframe computer system (this question must be updated… Anyway, I decided to keep the wording of the textbook). The processing times and the promised time for each of the jobs are listed here. Job 1 2 3 4 5 Processing time 40 min 2.5hr 20min 4hr 1.5hr Promised time 11:00am 2:00pm 2:00pm 1:00pm 4:00pm Assume that the current time is 10:00am. a. If the jobs are scheduled according to SPT, find the tardiness of each job and the mean tardiness of all jobs. b. Repeat the calculation in part (a) for EDD scheduling. Scheduling by SPT means that the jobs are processed in the sequence 3-1-5-2-4. SPT Sequencing Processing Job Time Completion Time Promised Time Tardiness(hrs) 3 20 min. 10:20 a.m. 2:00 p.m. 0 1 40 min. 11:00 a.m. 11:00 a.m
More Less
Unlock Document

Only 80% of the first page are available for preview. Some parts have been intentionally blurred.

Unlock Document
You're Reading a Preview

Unlock to view full version

Unlock Document

Log In


OR

Join OneClass

Access over 10 million pages of study
documents for 1.3 million courses.

Sign up

Join to view


OR

By registering, I agree to the Terms and Privacy Policies
Already have an account?
Just a few more details

So we can recommend you notes for your school.

Reset Password

Please enter below the email address you registered with and we will send you a link to reset your password.

Add your courses

Get notes from the top students in your class.


Submit