APS111H1 Lecture Notes - Lecture 4: Microsoft Project
Document Summary
Aps 112 lecture #4 project management part 2. To put in a milestone enter a time of zero days. Put things in by clicking on a cell. Everything should be connected in the end. Some tasks may require time before starting. Include final inspection & electrical inspection: if you need an expensive piece of equipment/important person, you need time to prepare. Resource graph: double click link/cell, select lag (task dependency, workers should have (ideally) 100% tasks for each day. To fix over allocation, select resource then level all .