Assignment #1
AP/ADMS3351 3.0
Section A
Prepared for Humayun Chaudhary
Assignment Due Date: June 17, 2013
Fill In Information Below:
Personal Work Statement
I, the undersigned:
warrant that the work submitted herein is my work and not the
work of others
acknowledge that we have read and understood the Senate Policy
on Academic Honesty
acknowledge that it is a breach of the University Regulations to
give and receive unauthorized assistance on a graded piece of
work
Name (typed)
York Student #
Signature
Yuqing Liu
210582708

Only pages 1-2 are available for preview. Some parts have been intentionally blurred.

Assignment 1
Question 1
Chapter 3, Problem 11 page 65
a.
b. The critical path is A-B-E-G.
c.
Duration
Crashed
Activity
Crash Costs
Total Direct
Costs
18
None
$0
$500
17
A
$20
$520
16
E
$30
$550
15
G
$50
$600
14
B and D
$60
$660
13
B and F
$100
$760
d. To add total direct cost and total indirect cost together the lowest one is either 15 or
16 weeks at a total cost of $850.
Duration
Total Direct Costs
Total Costs
18
$500
$900
17
$520
$870
16
$550
$850
15
$600
$850
14
$660
$860
13
$760
$910