Teldar Manufacturing Company is a diversified manufacturer thatmanufactures three products (M5, Z4, and I8) in a continuousproduction process. Senior management has asked the controller toconduct an activity-based costing study. The controller identifiedthe amount of factory overhead required by the critical activitiesof the organization as follows:
1
Activity
Activity Cost Pool
2
Production
$264,000.00
3
Setup
96,000.00
4
Material handling
9,600.00
5
Inspection
50,000.00
6
Product engineering
150,000.00
7
Total
$569,600.00
The activity bases identified for each activity are asfollows:
Activity
Activity Base
Production Machine hours Setup Number of setups Material handling Number of parts Inspection Number of inspectionhours Product engineering Number of engineeringhours
The activity-base usage quantities and units produced for thethree products were determined from corporate records and are asfollows:
Machine Number of Number of Number of Number of Hours Setups Parts Inspection Hours Engineering Hours Units M5 1,000 60 80 450 125 1,250 Z4 800 120 150 300 175 1,000 I8 400 220 250 250 200 500 Total 2,200 400 480 1,000 500 2,750
Each product requires 0.8 machine hour per unit.
Required: Complete the Activity Tablesfor M5, Z4 and I8. 1. Determine the activity ratefor each activity.* 2. Use the activity rates in(A) to determine the total and per-unit activity costs associatedwith all three products.* * If required, round allper-unit amounts to the nearest cent.
Required: Complete the Activity Tablefor M5. 1. Determine the activity ratefor each activity.* 2. Use the activity rates in(A) to determine the total and per-unit activity costs associatedwith all three products.* * If required, round all per-unit amounts to the nearestcent.
Teldar Manufacturing Company is a diversified manufacturer thatmanufactures three products (M5, Z4, and I8) in a continuousproduction process. Senior management has asked the controller toconduct an activity-based costing study. The controller identifiedthe amount of factory overhead required by the critical activitiesof the organization as follows:
1 | Activity | Activity Cost Pool |
2 | Production | $264,000.00 |
3 | Setup | 96,000.00 |
4 | Material handling | 9,600.00 |
5 | Inspection | 50,000.00 |
6 | Product engineering | 150,000.00 |
7 | Total | $569,600.00 |
The activity bases identified for each activity are asfollows:
Activity | Activity Base |
---|---|
Production | Machine hours |
Setup | Number of setups |
Material handling | Number of parts |
Inspection | Number of inspectionhours |
Product engineering | Number of engineeringhours |
The activity-base usage quantities and units produced for thethree products were determined from corporate records and are asfollows:
Machine | Number of | Number of | Number of | Number of | ||
Hours | Setups | Parts | Inspection Hours | Engineering Hours | Units | |
M5 | 1,000 | 60 | 80 | 450 | 125 | 1,250 |
Z4 | 800 | 120 | 150 | 300 | 175 | 1,000 |
I8 | 400 | 220 | 250 | 250 | 200 | 500 |
Total | 2,200 | 400 | 480 | 1,000 | 500 | 2,750 |
Each product requires 0.8 machine hour per unit.
Required: | |||||||
Complete the Activity Tablesfor M5, Z4 and I8.
|
Required: | ||||||||||||||||||||||||||||||
Complete the Activity Tablefor M5.
|