1
answer
0
watching
168
views

Teldar Manufacturing Company is a diversified manufacturer thatmanufactures three products (M5, Z4, and I8) in a continuousproduction process. Senior management has asked the controller toconduct an activity-based costing study. The controller identifiedthe amount of factory overhead required by the critical activitiesof the organization as follows:

1

Activity

Activity Cost Pool

2

Production

$251,598.00

3

Setup

92,035.00

4

Material handling

10,736.00

5

Inspection

49,833.00

6

Product engineering

136,230.00

7

Total

$540,432.00

The activity bases identified for each activity are asfollows:

Activity ActivityBase
Production Machine hours
Setup Number of setups
Material handling Number of parts
Inspection Number of inspection hours
Product engineering Number of engineering hours

The activity-base usage quantities and units produced for thethree products were determined from corporate records and are asfollows:

Machine Number of Number of Number of Number of
Hours Setups Parts Inspection Hours Engineering Hours Units
M5 970 63 84 489 123 1,354
Z4 802 123 138 272 170 1,044
I8 435 209 266 256 185 452
Total 2,207 395 488 1,017 478 2,850

Each product requires 0.72 machine hour per unit.

Required:
Complete the Activity Tablesfor M5, Z4 and I8.
1. Determine the activity ratefor each activity.*
2. Use the activity rates in(1) to determine the total and per-unit activity costs associatedwith all three products.*

* If required, round all per-unit amounts to the nearestcent.

Required:
Complete the Activity Table forM5.
1. Determine the activity ratefor each activity.*
2. Use the activity rates in(1) to determine the total and per-unit activity costs associatedwith all three products.*
* If required, round allper-unit amounts to the nearest cent.
M5
Activity Activity-
Base Activity Activity
Usage X Rate = Cost
Production
Setup
Material handling
Inspection
Engineering
Total activity cost
÷ Number of units ÷
Activity cost per unit
Required:
Complete the Activity Table forZ4.
1. Determine the activity ratefor each activity.*
2. Use the activity rates in(1) to determine the total and per-unit activity costs associatedwith all three products.*
* If required, round allper-unit amounts to the nearest cent.
Z4
Activity Activity-
Base Activity Activity
Usage X Rate = Cost
Production
Setup
Material handling
Inspection
Engineering
Total activity cost
÷ Number of units ÷
Activity cost per unit
Required:
Complete the Activity Table forI8.
1. Determine the activity ratefor each activity.*
2. Use the activity rates in(1) to determine the total and per-unit activity costs associatedwith all three products.*
* If required, round allper-unit amounts to the nearest cent.
I8
Activity Activity-
Base Activity Activity
Usage X Rate = Cost
Production
Setup
Material handling
Inspection
Engineering
Total activity cost
÷ Number of units ÷
Activity cost per unit

For unlimited access to Homework Help, a Homework+ subscription is required.

Irving Heathcote
Irving HeathcoteLv2
28 Sep 2019

Unlock all answers

Get 1 free homework help answer.
Already have an account? Log in

Related questions

Weekly leaderboard

Start filling in the gaps now
Log in