Teldar Manufacturing Company is a diversified manufacturer thatmanufactures three products (M5, Z4, and I8) in a continuousproduction process. Senior management has asked the controller toconduct an activity-based costing study. The controller identifiedthe amount of factory overhead required by the critical activitiesof the organization as follows:
1
Activity
Activity Cost Pool
2
Production
$251,598.00
3
Setup
92,035.00
4
Material handling
10,736.00
5
Inspection
49,833.00
6
Product engineering
136,230.00
7
Total
$540,432.00
The activity bases identified for each activity are asfollows:
Activity ActivityBase Production Machine hours Setup Number of setups Material handling Number of parts Inspection Number of inspection hours Product engineering Number of engineering hours
The activity-base usage quantities and units produced for thethree products were determined from corporate records and are asfollows:
Machine Number of Number of Number of Number of Hours Setups Parts Inspection Hours Engineering Hours Units M5 970 63 84 489 123 1,354 Z4 802 123 138 272 170 1,044 I8 435 209 266 256 185 452 Total 2,207 395 488 1,017 478 2,850
Each product requires 0.72 machine hour per unit.
Required: Complete the Activity Tablesfor M5, Z4 and I8. 1. Determine the activity ratefor each activity.* 2. Use the activity rates in(1) to determine the total and per-unit activity costs associatedwith all three products.* * If required, round all per-unit amounts to the nearestcent.
Required: Complete the Activity Table forM5. 1. Determine the activity ratefor each activity.* 2. Use the activity rates in(1) to determine the total and per-unit activity costs associatedwith all three products.* * If required, round allper-unit amounts to the nearest cent.
M5 Activity Activity- Base Activity Activity Usage X Rate = Cost Production Setup Material handling Inspection Engineering Total activity cost ÷ Number of units ÷ Activity cost per unit
Required: Complete the Activity Table forZ4. 1. Determine the activity ratefor each activity.* 2. Use the activity rates in(1) to determine the total and per-unit activity costs associatedwith all three products.* * If required, round allper-unit amounts to the nearest cent.
Z4 Activity Activity- Base Activity Activity Usage X Rate = Cost Production Setup Material handling Inspection Engineering Total activity cost ÷ Number of units ÷ Activity cost per unit
Required: Complete the Activity Table forI8. 1. Determine the activity ratefor each activity.* 2. Use the activity rates in(1) to determine the total and per-unit activity costs associatedwith all three products.* * If required, round allper-unit amounts to the nearest cent.
I8 Activity Activity- Base Activity Activity Usage X Rate = Cost Production Setup Material handling Inspection Engineering Total activity cost ÷ Number of units ÷ Activity cost per unit
Teldar Manufacturing Company is a diversified manufacturer thatmanufactures three products (M5, Z4, and I8) in a continuousproduction process. Senior management has asked the controller toconduct an activity-based costing study. The controller identifiedthe amount of factory overhead required by the critical activitiesof the organization as follows:
1 | Activity | Activity Cost Pool |
2 | Production | $251,598.00 |
3 | Setup | 92,035.00 |
4 | Material handling | 10,736.00 |
5 | Inspection | 49,833.00 |
6 | Product engineering | 136,230.00 |
7 | Total | $540,432.00 |
The activity bases identified for each activity are asfollows:
Activity | ActivityBase |
---|---|
Production | Machine hours |
Setup | Number of setups |
Material handling | Number of parts |
Inspection | Number of inspection hours |
Product engineering | Number of engineering hours |
The activity-base usage quantities and units produced for thethree products were determined from corporate records and are asfollows:
Machine | Number of | Number of | Number of | Number of | ||
Hours | Setups | Parts | Inspection Hours | Engineering Hours | Units | |
M5 | 970 | 63 | 84 | 489 | 123 | 1,354 |
Z4 | 802 | 123 | 138 | 272 | 170 | 1,044 |
I8 | 435 | 209 | 266 | 256 | 185 | 452 |
Total | 2,207 | 395 | 488 | 1,017 | 478 | 2,850 |
Each product requires 0.72 machine hour per unit.
Required: | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Complete the Activity Tablesfor M5, Z4 and I8.
|
Required: | |||||||
Complete the Activity Table forZ4.
|
Z4 | |||||
Activity | Activity- | ||||
Base | Activity | Activity | |||
Usage | X | Rate | = | Cost | |
Production | |||||
Setup | |||||
Material handling | |||||
Inspection | |||||
Engineering | |||||
Total activity cost | |||||
÷ Number of units | ÷ | ||||
Activity cost per unit |
Required: | |||||||
Complete the Activity Table forI8.
|
I8 | |||||
Activity | Activity- | ||||
Base | Activity | Activity | |||
Usage | X | Rate | = | Cost | |
Production | |||||
Setup | |||||
Material handling | |||||
Inspection | |||||
Engineering | |||||
Total activity cost | |||||
÷ Number of units | ÷ | ||||
Activity cost per unit |