The metering of a power customer was read and gave the following data:
KW-hr = 200,000 KVAR- hr.= 180,000 Maximum demand = 380 kW Billing days = 3
What is the load factor?
a. 68%
b. 80%
c. 73%
d. 62%
The metering of a power customer was read and gave the following data:
KW-hr = 200,000 KVAR- hr.= 180,000 Maximum demand = 380 kW Billing days = 3
What is the load factor?
a. 68%
b. 80%
c. 73%
d. 62%